Example Projects / Commercial / the centre:mk
We were contracted to decorate 1000m2 of perforated slatted steel ceiling at a height of 16m. All works had to be carried out at night within a 30-day time frame. All plant and equipment needed to be stored away after each shift to allow the centre to carry on trading without any disruption.
This involved the use of specialist access equipment, which was stored in a designated compound, erected and maintained by ESK. Each evening all surfaces were fully sheeted up before decorations commenced. Brewers protective coatings produced a specification tailored to both our and the clients requirement, which included quick drying water bourne products, which would fully adhere to the difficult substrate. This was achieved by degreasing the panels by hand, and then applying two coats of Rustoleum Noxyde, which achieved a smooth even matt finish. |
|||||
|
||||||