King’s Oak School – Bedford
![](https://www.esk-mk.co.uk/wp-content/uploads/2023/10/Kingsoak-Before.jpg)
We received a call from the new head teacher during the 1st week of the summer holidays seeking a contractor to redecorate 13 classrooms, circulation areas and staff rooms. Completion of the redecoration was required within 4 weeks to allow for the new floor coverings to be laid before the school re-opened in September 2014.
Works commenced the following Monday with a team of 9 decorators.
Dulux High Performance Eggshell was specified for the walls as this product is ‘super scuff resistant’ and withstands repeated scrubbing, ideal for a busy school. Works were completed on time and within the schools budget.